Report of Acting Director Inclusive Growth
Details
Decision Proposed
Birmingham 2022 – Update on the Perry Barr Regeneration Scheme FBC
Report of Acting Director Inclusive Growth
Cabinet : 27/07/21
Cabinet : 27/07/21
27/07/2021
To seek approval to an updated FBC which will reflect the changed circumstances for the Perry Barr Residential Scheme, and enable the progression of that and the associated wider Regeneration Scheme to completion.
30/11/20
Key Decisions
Capital cost in excess of £1m
Cabinet Report June 2019; Revised Full Business Case March 2020
Joint Cabinet Member Chief Officer Report approved 6 June 2019 - Perry Barr Regeneration Scheme Full Business Case.
Report to Cabinet approved 11 February 2020 – Commonwealth Games – Athletes Village Update (Contracting of Plot 7)
Report to Cabinet approved 17 March 2020 – Birmingham 2022 – Revised Perry Barr Regeneration Scheme FBC (RFBC)
Decision Maker
Committee
This section allows you to view the reports for the forward plan item.