On 11 February 2025 Cabinet:-
(i)
Approved the
project costs for the roofing and cladding replacement works at Coppice
Primary and Langley Special Schools at a total project cost not to exceed
£6,209,262;
(ii)
Approved the
Full Business Case appended to this report;
(iii)
Noted that a
Pre-Construction Services Agreement (PCSA) has been entered into with
Interclass Holdings Ltd for the initial design stage, which has been
completed for the estimated value of up to £182,575 and approved under Chief
Officer delegated authority on 13th March 2024. This figure included £57,592
Acivico fees and £5,477 EDI fees; and
(iv) Delegated
authority to the Director of Children and Families in consultation with the
Chief Operating Officer, the Director of Finance (Section 151 Officer) and
the Interim City Solicitor & Monitoring Officer (or their delegates) to
award a contract for the roofing and cladding replacement works to Interclass
Holdings Ltd for the estimated value of £5,767,376, (inclusive of £280,589
contingency). Authorised the Interim City Solicitor & Monitoring Officer
to complete all necessary documents to give effect to the above
recommendations.