Title:
Paradise Development Scheme
Include item on Forward Plan/ Key Decision
No
Urgent Decision - Not in Forward Plan
No
Details for Agenda Sheet
Report of the Corporate Director, Finance & Governance and the Assistant Director, Economy.
Implementation Date (not before meeting on)
Tue 22 Jan 2019
Purpose
To update Cabinet on the progress of the Paradise development, to ratify a decision made by the GBSLEP on funding and to provide the necessary approvals and arrangements to cover the next stage of the project. The report will outline the funding conditions, updated project management improvements and the summary findings of the independent review of the Paradise full business case.
Chief Officer Decision Maker
Directorate
Economy, Finance & Resources
Decision Outcome
-
Acting in its capacity as Accountable Body to the
GBSLEP, ratified the decision made by the GBSLEP Board at its meeting on 20 December 2019 to approve the award of up to
£51,277,000 of Enterprise Zone (EZ) grant funding to Birmingham City Council
for the delivery of Paradise project Phase 2;
-
Agreed to accept the award of up to £51,277,000
from the GBSLEP for the delivery of the Paradise scheme Phase 2 and approved
the prudential borrowing of that sum as part of a larger EZ Investment
Programme;
-
Noted and agreed to adhere to the GBSLEP conditions
of funding set out in section 3 to the report;
-
Approved the expenditure of up to £51,277,000 for continued delivery of
the Paradise project, and agreed to delegate to the Corporate Director, Economy in
conjunction with the Corporate Director, Finance and Governance authority to defray
these sums in line with the Council’s and GBSLEP’s approved governance
arrangements;
-
Agreed to delegate authority to the Corporate
Director, Finance and Governance, to enter into new or revised contracts with
the developer and Paradise Circus Limited Partnership (PCLP) to reflect the additional
funding and all terms and conditions attached to it;
-
Authorised the City Solicitor to prepare,
negotiate, execute and complete all relevant legal documentation to give effect
to the above decisions;
-
Approved the co-commissioning of an independent audit into the Paradise project
by the Council acting in its capacity as Accountable Body jointly with the
GBSLEP;
-
Noted progress with the delivery of the Paradise Circus development;
-
Noted that the project’s revised Full Business Case (FBC) is predicated
upon a further EZ funding request to the GBSLEP for delivery of Phase the
report does not seek approval to Phase 3 expenditure, which will be the subject
of a further Green Book compliant FBC to be submitted once the designs and
costs are appropriately developed;
-
Noted that the FBC has been reviewed separately by
the Department for Business, Energy and Industrial Strategy and that the
revised agreement addresses their concerns.
THE
DEADLINE FOR CALL IN IS 1600 HOURS ON MONDAY 28 JANUARY 2019.
Is the Decision Maker Aware of the Decision:
No
Is the Head of Services Aware of the Decision:
No
Is Decision County Wide:
No
Would the recommended decision be contrary to the budget and policy framework:
No
Additional Information
Decision Criteria
This Decision does not contain any decision criteria records.
Wards
Acocks Green; Allens Cross; Alum Rock; Aston; Balsall Heath West; Bartley Green; Billesley; Birchfield; Bordesely & Highgate; Bordesely Green; Bournbrook & Selly Park; Bournville & Cotteridge; Brandwood & Kings Heath; Bromford & Hodge Hill; Castle Vale; Druids Heath & Monyhull; Edgbaston; Erdington; Frankley Great Park; Garretts Green; Glebe Farm & Tile Cross; Gravelly Hill; Hall Green North; Hall Green South; Handsworth; Handsworth Wood; Harborne; Heartlands; Highter's Heath; Holyhead; Kings Norton North; Kings Norton South; Kingstanding; Ladywood; Longbridge & West Heath; Lozells; Moseley; Nechells; Newtown; North Edgbaston; Northfield; Oscott; Perry Barr; Perry Common; Pype Hayes; Quinton; Rubery & Rednall; Shard End; Sheldon; Small Heath; Soho & Jewellery Quarter; South Yardley; Sparkbrook & Balsall Heath East; Sparkhill; Stirchley; Stockland Green; Sutton Four Oaks; Sutton Mere Green; Sutton Reddicap; Sutton Roughley; Sutton Trinity; Sutton Vesey; Sutton Walmley & Minworth; Sutton Wylde Green; Tyseley & Hay Mills; Ward End; Weoley & Selly Oak; Yardley East; Yardley West & Stechford
Topics
This Decision does not contain any Topic records
Overview and Scrutiny
This Decision does not contain any Overview and Scrutiny records.
This section allows you to view the reports for the Decision.
This section displays the history of the Decision.
Decision History
02/01/2019 16:11:38 | Liz Blackburn | Business Item Created | |
02/01/2019 16:11:38 | Liz Blackburn | Committee Added | Cabinet |
02/01/2019 16:11:43 | Liz Blackburn | Workflow Assigned | Workflow ID 5F2FD9BB-1B98-4DAB-83AA-04BA53CF8C56 |
02/01/2019 16:13:14 | Liz Blackburn | Ward Added | Acocks Green |
02/01/2019 16:13:14 | Liz Blackburn | Ward Added | Allens Cross |
02/01/2019 16:13:14 | Liz Blackburn | Ward Added | Alum Rock |
02/01/2019 16:13:14 | Liz Blackburn | Ward Added | Aston |
02/01/2019 16:13:15 | Liz Blackburn | Ward Added | Balsall Heath West |
02/01/2019 16:13:15 | Liz Blackburn | Ward Added | Bartley Green |
02/01/2019 16:13:15 | Liz Blackburn | Ward Added | Billesley |
Approval/Comments
Approve |
Liz Blackburn
|
Wed 2 Jan 2019 - 04:20
|
Fri 31 Dec 9999
|
Wed 2 Jan 2019 - 04:20
|
Accepted
|
|