Decision Details

  • General
  • Reports

This section allows you to view the general details of a Decision

Details

Status:
Implemented
Title:
Metro Westside Extension and Associated Measures - Full Business Case
Include item on Forward Plan/ Key Decision
Yes
Reference:
005743/2019
Urgent Decision - Not in Forward Plan
No
Details for Agenda Sheet
Report of Director Inclusive Growth
Implementation Date (not before meeting on)
Tue 12 Feb 2019
Purpose
To note the development of the current Metro extension to 54 Hagley Road and seek approval to the Associated Measures required to facilitate this Metro extension.
Key Portfolio
OLD - Transport and Environment
Decision Maker
Chief Officer Decision Maker
Reason For Key Decision

over £500,000 revenue

significant effect on 2 or more Wards

Relevant Documents

List of previous related Reports:

  • Report to Cabinet 10th January 2005, City Centre Bus Mall – Moor Street Queensway

  • Report to Cabinet 13th November 2006, Metro, Birmingham City Centre Extension - Birmingham City Council / Centro Development Agreement

  • Report to Cabinet Committee (Procurement), 25th March 2010, Ladywood Circus Junction Improvement Scheme – Full Business Case

  • Report to Cabinet, 14th March 2011, Midland Metro Birmingham City Centre Extension and Associated Highway Works

  • Report to Cabinet Member for Transport, Environment and Regeneration: City Centre Quality Partnership Scheme: February 2012

  • Report to Cabinet 21st October 2013, Metro Extension to Centenary Square and Associated Works – Project Definition Document

  • Cabinet Report, Bus Lane Enforcement – Full Business Case, 4 March 2013

  • PEP - Bus Lane Review: August 2014

  • Report to Cabinet Member for Development, Transport and the Economy & Cabinet Member for Commissioning, Contracting and Improvement jointly with the Deputy Chief Executive, 6th March 2015, Signalisation of Five Ways Roundabout & Spring Hill Traffic Management

  • Cabinet Report, Updated Transportation and Highways Capital Funding Strategy 2015/16 to 2020/21 Programme Definition Report, 16 February 2016

  • Highlight Report - Bus Lane Enforcement Review, July 2016

  • Report to Cabinet, Bus Lane Enforcement (Tranche 1) - Full Business Case, 24 January 2017

  • Report to Cabinet Members for Transport and Roads and Value for Money and Efficiency jointly with the Corporate Director, Economy, 3rd August 2017, Holloway Circus Improvement: Revisions to  Full Business Case and Contract Award

  • Report of Assistant Director, Transportation and Connectivity under Delegated Authority,8th August 2018: Metro Edgbaston Extension Complementary Highways Works, Construction under Section 278 Agreement

  • Report of Assistant Director, Transportation and Connectivity under Delegated Authority,15th August 2018: Metro Edgbaston Extension Complementary Highways Works, Objections to Traffic Regulation Orders – Approval to Proceed Notwithstanding

Decision Type:
Committee
Decision Maker:
Cabinet
Directorate
Economy
Other Information
Private Reason
Decision Outcome

On 12 February 2019, Cabinet:-

 

(i)       Acting on behalf of the Council in its capacity as Highway Authority, noted the route of the Westside Metro Extension and authorised the Assistant Director, Transportation and Connectivity (ADTC), in consultation with the Leader of the Council and the Cabinet Member for Transport and Environment (CMTE), to agree the details of the route with West Midlands Combined Authority (WMCA)/Transport for West Midlands (TfWM) who are acting in their capacity as project sponsors/funders as set out in Appendix B to the report;

 

(ii)       Approved the required Complementary Highways Works (CHW) proposed noting that some of these CHW have already been approved to enable the WMCA/TfWM to commence works to meet the Metro delivery deadlines as set out at Appendix C to the report;

 

 

(iii)      Authorised the ADTC to develop additional CHW that may be required with WMCA/TfWM, in consultation with the CMTE, including preparing and entering into the associated Section 278 Agreements for the CHW and Traffic Regulation Order (TRO) requirements;

 

(iv)      Approved the implementation of up to 17 proposed enforcement cameras as set out in Appendix D, noted that the procurement of the camera enforcement equipment will be through the existing Council Information Technology and Digital Service (IT&DS) contract on behalf of WMCA/TfWM and that the Capital cost will be funded by the WMCA/TfWM;

 

(v)      Approved the Council taking ownership of the enforcement cameras equipment provided by WMCA/TfWM as Highway Authority assets and authorises the ADTC to be responsible for the ongoing operation of the enforcement activity and the operational income and expenditure including future maintenance obligations (as detailed within Appendix A Section 2 to the report) and notes that any net surplus will be utilised in line with regulations;

(vi)      Acting on behalf of the Council in its capacity as Highway Authority approved the proposed Metro Westside Extension and Associated Measures, as set out in Appendices B, C and D to the report, being delivered by the Midland Metro Alliance (MMA), or approved contractors as identified in Appendix A to the report, on behalf of the WMCA/TfWM;

 

(vii)     Approved the Council taking responsibility for the ongoing maintenance resulting from the highways works and noted the proposed commuted sum to be provided by the WMCA/TfWM to fund these costs and the financial implications for the recommendations in the report;

 

(viii)    Authorised the City Solicitor to negotiate, execute, seal and complete all necessary documentation to give effect to the above decisions.

 

THE DEADLINE FOR CALL IN IS 1600 HOURS ON FRIDAY 15 FEBRUARY 2019.
Is the Decision Maker Aware of the Decision:
No
Is the Head of Services Aware of the Decision:
No
Is Decision County Wide:
No
Would the recommended decision be contrary to the budget and policy framework:
No
Decision Options:

Additional Information

Reg 10
Reg 11

Decision Criteria

This Decision does not contain any decision criteria records.

Wards

Edgbaston; Ladywood; North Edgbaston

Topics

This Decision does not contain any Topic records

Overview and Scrutiny

Sustainability and Transport Overview and Scrutiny Committee

This section allows you to view the reports for the Decision.

This section displays the history of the Decision.

Decision History

Date & Time CreatedUser Full NameStatus DescriptionDetails
123
 Page 1 of 3, items 1 to 10 of 23.
23/10/2018 13:41:05Dave ArnoldBusiness Item Created 
23/10/2018 13:41:05Dave ArnoldCommittee AddedCabinet
23/10/2018 13:41:05Dave ArnoldMeeting Added22/01/2019 10:00AM
23/10/2018 13:41:09Dave ArnoldWorkflow AssignedWorkflow ID 7A91271D-F37B-418A-AAF1-360137E2D647
23/10/2018 13:41:49 Status ChangedDecision Scheduled [1]
23/10/2018 13:43:08Dave ArnoldWard AddedEdgbaston
23/10/2018 13:43:08Dave ArnoldWard AddedLadywood
23/10/2018 13:43:08Dave ArnoldWard AddedNorth Edgbaston
23/10/2018 13:44:22Dave ArnoldCommittee AddedSustainability and Transport Overview and Scrutiny Committee
23/10/2018 13:48:40Dave ArnoldConsultation/Comments Edited 

Approval/Comments

Workflow ActionUserRequested DateResponse Due DateResponded DateResponseResponse Comment
Approve Dave Arnold Tue 23 Oct 2018 - 01:41 Fri 31 Dec 9999 Tue 23 Oct 2018 - 01:41 Accepted