On the 12 May 2025, the Cabinet Member for Children, Young People & Families:
(i) Approved the project costs for the window replacement and toilet refurbishment works at Lindsworth School, at a cost of up to £374,157.This is inclusive of £37,215 Acivico professional fees and £10,898 Education Infrastructure capitalisation fees.
ii) Approved the Full Business Case appended to this report.
iii) Approved the award of a contract for the window replacement and toilet refurbishment works at Lindsworth School, to Graham Asset Management Limited for the estimated value of £326,044 (this is inclusive of £30,750 contingency) for a construction period of 14 weeks commencing in May 2025; and
iv) Authorised the Interim City Solicitor and Monitoring Officer to execute and complete all necessary legal documents to give effect to the above recommendation.
THE DEADLINE FOR CALL-IN IS 1600 HOURS ON THURSDAY 15 MAY 2025.