On the 13 June 2025 the Cabinet Member for Children Young People and Families:
1. Approved the project costs for the boiler replacement works at Cherry Orchard Primary School, at a cost of up to £323,908. This is inclusive of £11,339 Acivico professional fees and £9,434 Education Infrastructure capitalisation fees;
2. Approved the Full Business Case appended to this report;
3. Approved the award of a contract for the boiler replacement works at Cherry Orchard Primary School, to Dodd Group Limited for the estimated value of £303,135 (this is inclusive of £25,000 contingency) for a construction period of 12 weeks commencing in July 2025;
4. Noted that the Boiler Replacement project at Cherry Orchard Primary School was on a Planned Programme Activities Report (PPAR) approved by Cabinet on 21st January 2025; and
5. Authorised the Interim City Solicitor and Monitoring Officer to execute and complete all necessary legal documents to give effect to the above recommendation.
NB: THE DEADLINE FOR CALL IN ENDS ON WEDNESDAY 18 JUNE 2025 AT 1600 HOURS.