On 22
March 2022, Cabinet:-
(i) Approved the proposal
for the establishment of a Trust capital programme front loaded to manage the
required estate changes to increase capacity in the children’s homes due to
changing legislation; improving the condition of child focused accommodation.
This requires capital investment of £1.650m 2022/23, £1.300m in year two and an
ongoing maintenance programme of £1.100m business as usual position from
2024/25 until 2026/27, a total of £6.250m;
(ii) noted that the
programme is made up of a 5-year rolling programme of maintenance, major works,
capital investment in new accommodation, resourcing and dilapidations;
(iii) delegated authority to
approve the procurement strategy and award of contracts for the improvement of
property estate to the successful provider(s) will be managed in line with the
current delegated authority between the Children’s Trust and Council;
(iv) authorised the Acting
City Solicitor to negotiate, execute and complete all necessary documents to
give effect to the above recommendations.
THE
DEADLINE FOR CALL IN IS 1600 HOURS ON MONDAY 28 MARCH 2022