Status:
Implemented
Title:
HS2 Curzon Station Enhanced Public Realm Project
Include item on Forward Plan/ Key Decision
Yes
Reference:
006208/2019
Urgent Decision - Not in Forward Plan
No
Details for Agenda Sheet
Report of Director Inclusive Growth
Implementation Date (not before meeting on)
Tue 29 Oct 2019
Purpose
To accept a capital grant from the Greater Birmingham and Solihull Local Enterprise Partnership Enterprise Zone (GBSLEP EZ) funding to deliver the preferred option for the public realm works surrounding the new Curzon Street station to create new squares and spaces that will enhance the setting of both the station and enhance connectivity to Digbeth, Eastside and the city centre.
Key Portfolio
Leader
Decision Maker
Chief Officer Decision Maker
Reason For Key Decision

over £1m capital  

Relevant Documents

HS2 Station Public Realm Programme and Curzon Station Metro Stop 2018               Curzon Masterplan 2014                           Curzon Investment Plan 2016

Decision Type:
Committee
Decision Maker:
Cabinet
Directorate
Inclusive Growth
Other Information
Private Reason
Decision Outcome

On 29 October 2019, Cabinet:-

 

(i) Accepted an annual revenue grant from the Greater Birmingham and Solihull Local Enterprise Partnership (GBSLEP) to support the costs of borrowing of up to £26,172,419 to deliver the HS2 Birmingham Curzon Station Enhanced Public Realm project, subject to the funding conditions set out in the offer letter at Appendix 1 to the report;

(ii) In its role as delivery partner for the project, approved City Council prudential borrowing up to £26,172,419 to fund delivery of the HS2 Birmingham Curzon Station Enhanced Public Realm project as set out in the outline business case and key appendices attached as Appendix 2 to the report. This includes up-front funding of £222,764 to develop the Full Business Case;

(iii) Under Part D2.5 of the Constitution, approved the entering into single contract negotiations jointly by the Director - Inclusive Growth and Chief Finance Officer with HS2 Ltd for up to £22,885,000 for the delivery of the HS2 Birmingham Curzon Station Enhanced Public Realm project;

(iv) Noted that a Full Business Case will be presented to Cabinet once the full scheme cost is defined as part of Stage 1 of the contractor procurement to design and build the Station in 2021. This will seek authority to enter into a Contract with HS2 Ltd for delivery of the enhanced public realm;

(v) Agreed to delegate the agreement of Heads of Terms with HS2 Ltd for the delivery of the HS2 Curzon Station Enhanced Public Realm project to the Leader and the Cabinet Member for Finance and Resources;

(vi) Noted that an independent cost consultant, Acivico Ltd, will be appointed to undertake an appraisal of all project costs in line with existing contractual arrangements to ensure they are value for money. The cost for this is included within the up-front funding;

(vii) Authorised the City Solicitor to negotiate, execute, seal and complete all necessary documents in connection with the above decisions.

 

THE DEADLINE FOR CALL IN IS 1600 HOURS ON MONDAY 4 NOVEMBER 2019.

Is the Decision Maker Aware of the Decision:
No
Is the Head of Services Aware of the Decision:
No
Is Decision County Wide:
No
Would the recommended decision be contrary to the budget and policy framework:
No
Decision Options:

Additional Information

Reg 10
Reg 11

Decision Criteria

This Decision does not contain any decision criteria records.

Wards

Ladywood; Nechells

Topics

This Decision does not contain any Topic records

Overview and Scrutiny

Economy and Skills Overview and Scrutiny Committee
Resources Overview and Scrutiny Committee

This section allows you to view the reports for the Decision.

Reports

  1. pdf HS2 Curzon Station Enhanced Public Realm Project (296Kb)
    1. pdf Appendix 1 - OBC Approval Letter (158Kb)
    2. pdf HS2 Curzon Station Enhanced Public Realm Report Appendix 2 (4608Kb)
    3. pdf Exempt Appendix 3 - Private Report
    4. pdf Exempt Appendix 4 - Cost Appraisal Report - Private Report
    5. pdf Appendix 5 - Curzon Public Realm EA (120Kb)

This section displays the history of the Decision.

Decision History

Date & Time CreatedUser Full NameStatus DescriptionDetails
123
 Page 1 of 3, items 1 to 10 of 25.
31/01/2019 14:28:38Janet HinksBusiness Item Created 
31/01/2019 14:28:38Janet HinksCommittee AddedCabinet
31/01/2019 14:28:38Janet HinksMeeting Added16/04/2019 10:00AM
31/01/2019 14:28:44Janet HinksWorkflow AssignedWorkflow ID 6C12237B-0BFE-4798-A8F8-4F51367D875D
31/01/2019 14:29:13 Status ChangedDecision Scheduled [1]
31/01/2019 14:29:58Janet HinksWard AddedLadywood
31/01/2019 14:29:58Janet HinksWard AddedNechells
31/01/2019 14:31:01Janet HinksContacts Edited 
31/01/2019 14:36:36Janet HinksConsultation/Comments Edited 
05/02/2019 15:18:25Janet HinksOS Committee AddedEconomy and Skills Overview and Scrutiny Committee

Approval/Comments

Workflow ActionUserRequested DateResponse Due DateResponded DateResponseResponse Comment
Approve Janet Hinks Thu 31 Jan 2019 - 02:29 Fri 31 Dec 9999 Thu 31 Jan 2019 - 02:29 Accepted