On 14
December 2021, Cabinet:-
(i) noted the acceptance of
£4.474m of GBSLEP EZ funding approved on 7 March 2018 by GBSLEP Programme
Delivery Board as a contribution towards the delivery of the Metro Extension to
Centenary Square scheme, noting that this is in addition to £15.950m already
secured;
(ii) approved the City
Council, acting as the Accountable Body for the GBSLEP Enterprise Zone,
prudentially borrowing up to £4.474m to contribute towards the delivery of the
Metro Extension to Centenary Square for both the enhanced materials used within
this Metro Extension and to cover a reduced contribution from the Paradise
Development;
(iii) authorised the Director
of Council Management to passport this funding to the WMCA, as payment for both
the enhanced materials used within this Metro Extension and to cover a reduced
contribution from the Paradise Development, subject to the Deed of Variation
being signed by the City Council and WMCA;
(iv) authorised the City
Solicitor to negotiate, execute, seal and complete all necessary documentation
to give effect to the above recommendations.