Full Business Case and Contract Award for Anglesey School - Boiler Replacement Works
Include item on Forward Plan
No
Item Contains Exempt/Private Reports
No
Urgent Decision - Not in Forward Plan
No
Details for Agenda Sheet
Report of the Interim Executive Director of Children & Families
Implementation Date (not before meeting on)
Tue 21 Jul 2026
Key Portfolio
------ N/A ------
Decision Maker
Not Applicable
Chief Officer Decision Maker
------ N/A ------
Decision Maker:
Cabinet Member
Decision Outcome
On 21 July 2026, the Cabinet Member for Children Young People
and Families:
1. Approved the total project costs and
spend of up to £301,908 for boiler replacement works at Anglesey School funded
from the School Condition Allocation (SCA).
2. Approved the Full Business Case appended
to the report as Appendix 1.
3. Approved the award of a contract by
direct award using the Constructing West Midlands Capital Works Framework
Agreement for the boiler replacement works at Anglesey School for the value of
£246,632 (plus a contingency of £30,000 for any unforeseen circumstances) to
Dodd Group (Midland) Ltd for a construction period of 12 weeks commencing in
July 2026 with completion anticipated in October 2026.
4. Noted that any VAT attributable to the
costs payable by the Council is reclaimable under Section 33 of the VAT Act
1994.
5. Authorised the City Solicitor (or their
delegate) to execute and complete all necessary documents to give effect to the
above recommendations.
NB: THE DEADLINE FOR CALL IN ENDS ON FRIDAY 24 JULY 2026 AT 1600 HOURS.
Would the recommended decision be contrary to the budget and policy framework:
No
Additional Information
Decision Criteria
This Decision does not contain any decision criteria records.
Wards
This Decision does not contain any Ward records.
Topics
This Decision does not contain any Topic records
Overview and Scrutiny
This Decision does not contain any Overview and Scrutiny records.
This section allows you to view the reports for the Decision.
This section displays the history of the Decision.
Decision History
| 21/07/2026 13:50:17 | Errol Wilson | Business Item Created | |
| 21/07/2026 13:50:17 | Errol Wilson | Committee Added | Cabinet Member |
| 21/07/2026 13:50:28 | Errol Wilson | Status Changed | Decision Scheduled [1] |
| 21/07/2026 13:50:50 | Errol Wilson | Meeting Added | 21/07/2026 2:00PM |
| 21/07/2026 13:51:45 | Errol Wilson | Report Added | Document ID 345903: Angelsey School CMR for Boiler Replacement Works - 020726 |
| 21/07/2026 13:56:45 | Errol Wilson | Status Changed | Decision Proposed [2] |
| 21/07/2026 15:19:05 | Michelle Edwards | General Details Edited | |
Approval/Comments
No history found.