Decision Details

  • General
  • Reports

This section allows you to view the general details of a Decision

Details

Status:
Implemented
Title:
A457 Dudley Road Improvement Revised Scheme – Western Road Junction Full Business Case
Include item on Forward Plan/ Key Decision
Yes
Reference:
008401/2021
Urgent Decision - Not in Forward Plan
No
Details for Agenda Sheet
Report of Acting Director Inclusive Growth
Implementation Date (not before meeting on)
Tue 16 Mar 2021
Purpose
To approve the Full Business Case and Delivery of the Dudley Road Improvement Revised Scheme - Western Road Junction as Phase 1 Advance Works
Key Portfolio
OLD - Transport and Environment
Decision Maker
Chief Officer Decision Maker
Reason For Key Decision
Above £1m capital
Relevant Documents
Dudley Road Improvement PDD Cabinet Report Public, Dudley Road Additional Land Requirements Cabinet Report Public
Decision Type:
Committee
Decision Maker:
Cabinet
Directorate
Inclusive Growth
Other Information
Private Reason
Decision Outcome

On 16 March 2021, Cabinet:-

 

  1. Approved the Full Business Case (FBC) for the Dudley Road Improvement Revised Scheme - Western Road Junction Phase 1 Advanced Works at a total estimated capital cost of £5.100m, as detailed in Appendix A, to the report and shown on the scheme plan in Appendix D, to the report, noting that this is in line with the preferred option approved by Cabinet in the OBC for the Dudley Road Improvement Scheme on 10th November 2020;

  2. Delegated authority to the Assistant Director Transport and Connectivity to place orders with the following statutory undertakers to enable utility diversions to take place subject to the works cost being within budget:

     

    – Western Power Distribution for electricity apparatus ;

     

    – BT for Openreach civils cables ;

     

    – Vodaphone for telecommunications apparatus ;

     

    – Cadent for gas mains apparatus ;

     

    – Virgin Media for telecommunications and fibre optic cables ;

     

    – Seven Trent for water and drainage

     

  3. Delegated authority to the Assistant Director Transport and Connectivity to place orders with McPhilips Wellington Ltd under the current contract to deliver accommodations and demolition works for the MOT Garage, Windmill Public House and adjacent retail properties as previously outlined in the OBC approved on 10th November 2020 subject to the works cost being within budget;

     

  4. Authorised the City Solicitor (or their delegate) to complete all relevant documents necessary to give effect to the above decisions.

     

THE DEADLINE FOR CALL IN IS 1600 HOURS ON MONDAY 22 MARCH 2021

Is the Decision Maker Aware of the Decision:
No
Is the Head of Services Aware of the Decision:
No
Is Decision County Wide:
No
Would the recommended decision be contrary to the budget and policy framework:
No
Decision Options:

Additional Information

Reg 10
Reg 11

Decision Criteria

This Decision does not contain any decision criteria records.

Wards

Ladywood; North Edgbaston; Soho & Jewellery Quarter

Topics

This Decision does not contain any Topic records

Overview and Scrutiny

Sustainability and Transport Overview and Scrutiny Committee

This section displays the history of the Decision.

Decision History

Date & Time CreatedUser Full NameStatus DescriptionDetails
12
 Page 1 of 2, items 1 to 10 of 16.
17/12/2020 17:03:16Janet HinksBusiness Item Created 
17/12/2020 17:03:16Janet HinksCommittee AddedCabinet
17/12/2020 17:03:16Janet HinksMeeting Added16/03/2021 10:00AM
17/12/2020 17:04:18Janet HinksStatus ChangedDecision Scheduled [1]
17/12/2020 17:05:22Janet HinksWard AddedLadywood
17/12/2020 17:05:22Janet HinksWard AddedNorth Edgbaston
17/12/2020 17:05:22Janet HinksWard AddedSoho & Jewellery Quarter
17/12/2020 17:08:50Janet HinksConsultation/Comments Edited 
17/12/2020 17:09:25Janet HinksContacts Edited 
17/12/2020 17:09:56Janet HinksOS Committee AddedSustainability and Transport Overview and Scrutiny Committee

Approval/Comments

No history found.