On the 27 May 2022 the Cabinet Members for Children Young People and Families and for Finance and Resources:
1. Approved the capital works at The City of Birmingham School at a total project cost of up to £765,996 including Acivico professional fees of £83,876 and Education Infrastructure fees of £22,311;
2. Approved the Full Business Case appended to this report;
3. Approved the award of a contract to Graham Asset Management Ltd using Constructing West Midlands 2 (CWM2) Framework, up to the value of £621,309 for the works to commence, and to release contingencies and place further orders for unforeseen work related to the project up to £38,500 if required;
4. Approved the value of £83,876 to Acivico for professional services and statutory fees; and
5. Authorised the Acting City Solicitor and Monitoring Officer to negotiate, execute and complete all necessary documents to give effect to the above recommendations.
NB: THE DEADLINE FOR CALL IN IS WEDNESDAY 1 JUNE 2022 AT 1600 HOURS